Kryton International | Experts in Crystalline Concrete Waterproofing, Repair &  Protection. Home | About Us | Krystol® FAQ | Contact | Careers
 
Infinite Menus, Copyright 2006, OpenCube Inc. All Rights Reserved.
 
 
Projects
 
Below-Grade
 
Water Containment
 
Aquatic facilities
 
Bridges & Dams
 
Tunnels & Pipelines
 
Above-Grade
 
Other Projects
   
  Find a Project by Country:
 
   
 
Subscribe our Regional E-News today!

 


Tunnels & Subways

JFK Airport, pedestrian tunnel
New Yourk City, USA

BACKGROUND
In 1999, American Airlines began construction on a $1.4 billion, 2.2-million-square-foot terminal complex to replace Terminals 8 and 9 at New York's JFK Airport. When completed in 2007, the complex will serve domestic and international passengers on three concourses, and will include a customs and immigrations facility, a 10,000 square-foot retail and concession space, and a new 1,900-space parking garage. To allow for uninterrupted passenger service, the complex is being built in four stages.

Part of the terminal construction involved building a new 1,500-foot-long, 150-foot-wide concrete pedestrian tunnel, which runs 25 feet below finished grade with a water height of 12 feet at high tide. During the original construction of the tunnel, conventional PVC waterstop and membranes were used to waterproof the structure.

Before long, however, shrinkage cracks began to form and they, along with the cold joints and construction joints in the walls and floors, began to leak. Over the next 18 months, the foundation contractor tried numerous solutions to fill the cracks and stop the leakage. Despite spending many thousands on repair solutions, the cracks continued to grow and the tunnel continued to leak.

SOLUTION
After a number of failed repair attempts, the foundation contractor contacted the Crystal Group, a Kryton International distributor in New York. The Crystal Group offered to undertake a 50-foot test repair using Krystol Crack Repair & Waterproofing System.

Krystol T1/T2 is a cementitious mixture that can be brush-applied to existing concrete structures to repair cracks, fortify and waterproof the concrete and protect it against contamination and steel reinforcement corrosion. After application, chemicals from Krystol T1/T2 are absorbed into the concrete by the natural wicking action of concrete. Once inside the concrete, the chemicals cause crystals to grow, self-sealing cracks and filling the spaces between concrete particles, permanently blocking the movement of water in all directions.

The majority of active Krystol chemicals migrate into the concrete within the first 28 days, meaning the surface-applied slurry can be completely removed from the surface after this time without impacting its waterproofing properties. Krystol T1/T2 can be applied to positive or negative surfaces, making it well-suited for repairing sub-grade structures where access to outside walls may be difficult or impossible.

Once the 50-foot test repair proved watertight, the project team gave the go ahead for full repairs to begin. The repair team began by grinding out the cracks and joints to remove the epoxy and other materials that had been used in an attempt to stop the leakage. Honeycombed sections where air had not entrained properly were also chipped out. The Krystol T1/T2 system was applied on all cracks and joints successfully. Even cracks greater than .75 mm were able to self-seal when allowed adequate time for crystal growth to occur.

After the shrinkage cracks and cold and construction joints were repaired, the Crystal Group used Krystol T1/T2 to repair a shifting armour joint, which connected two 500-foot concrete tunnel sections. The 87 feet of repairs were made more difficult by freezing temperatures and a continuous flow of 40-degree ground water at 15 PSI. Furthermore, the JFK project team wanted to pressure-test the repairs just 7 days after completion, which is earlier than recommended. Despite the adverse conditions and shortened timeframe, the test was successful and the armour joint proved watertight.

Location New York, New York, USA
Owner American Airlines
Architect & Engineer DMJM Harris
Repair Contractor The Crystal Group, LLC
Contractor VRH TORCON

Back to Top

 

 


The $1.4 BB complex will serve domestic and international passengers on three concourses, and will include a customs and immigrations facility, a 10,000 square-foot retail and concession space, and a new 1,900-space parking garage.


Part of the terminal construction involved building a new 1,500-foot-long, 150-foot-wide concrete pedestrian tunnel, which runs 25 feet below finished grade with a water height of 12 feet at high tide.


  Home | Products | Solutions | Support | Projects | Distribution | About Us | Krystol® FAQ | Contact | News |
Search | Site Map | Terms of Use | Privacy PolicyCopyright © 2006 Kryton International Inc. All rights reserved.