Toll Free +1.800.267.8280 Tel +1.604.324.8280 info@kryton.com

Projects

Case Studies


Location

Park Hyatt Hotel and Condominium Complex, Cathedral Place, Melbourne, Australia

Owner

Lustig & Moar Group

Engineer

Bonacci Winwood Group Pty Ltd.

Architect

The Buchan Group

General Contractor

Grocon Pty Ltd.

Concrete Supplier

Grollo Premixed Pty Ltd.

Distributor

Kryton Australia Pty Ltd.

Search Keywords:

Park Hyatt Hotel

Park Hyatt Hotel and Condominium Complex, Cathedral Place, Melbourne, Australia

The Park Hyatt Hotel.

Background

The complex at Cathedral Place has five (5) levels of underground parking. The structure was designed to extend to each of the site boundaries and conventional tanking of the building could not be considered. The use of KIM™ concrete for tanking the building allowed maximum use of the available site as the concrete was placed directly against the excavation wall and no other waterproofing method was necessary.

Solution

In 1997, construction began with 2400 cubic meters (3,000 cubic yards) of KIM concrete requiring 12,000 kg (26,500 lbs) of KIM. The application has been inspected each year and the parking structure remains completely dry.