The Horka Dam built in 1985 had water leakage problems in the maintenance tunnels well below grade. The maintenance tunnels required waterproofing for 1550 m2 of existing concrete.
SOLUTION
Krystol™ T1 and T2 were used on existing below grade concrete. Since the Krystol™ application in 1997 no leaks or wet spots have been observed.
| Location |
West Czech Region, Czech Republic |
| Distributor |
Fosroc Veritech, Prague, Czech Republic |
| Applicator |
Realcrete, s.r.o. |
| Engineer |
Vltava River Administration, Inc. |